• Cut ground jumper to length, allowing 1/2" overlap on each end
of twisted grounding wire.
• Slide SolderSleeve connectors onto ground wires and jumper.
• Heat SolderSleeve connectors until solder has melted. • Before and after re-installing the mortar and tile run the three
standard QuickNet commissioning tests from the cold lead
wire at the QuickStat Thermostat and record the results in the
commissioning log.
• Continue the QuickNet System installation following the
QuickNet and QuickStat Installation manuals.
27 28
29 30
• Center the 4 black heat-shrinkable tubes over the installed
SolderSleeve connectors.
• Using the heat gun, shrink in place.
26
• Heat SolderSleeve connectors until solder and adhesive have
melted.
• Allow to cool, then repeat for second jumper wire.